Risks we've caught

Real failure modes. Real money. Real previous engagements.

Below are anonymised examples of risks our senior engineers have caught on previous hyperscale builds. Programme names and client identities are removed; capacity, region and date are real.

These are the patterns Upterix is built to find.

Anonymised cases
6

Anonymised cases

Recovered value across cases
€9.8M+

Recovered value across cases

Weeks of schedule recovered
10+

Weeks of schedule recovered

Anonymised · no client identities
100%

Anonymised · no client identities

Cases drawn from 20212023, spanning 3 distinct programme years.
Case #
Caught pre-construction
  • 40MW
  • Northern Europe
  • 2023

Undersized cable trays caught at design-review gate

Cable tray sizing assumed 2019 power densities; project was specified for 2024 GPU racks at 75 kW each. Caught in pre-tender review.

Recovered value
€2.3M

rework avoided

6 wk

schedule recovered

Case #
Caught pre-construction
  • 60MW
  • Western Europe
  • 2022

Cooling architecture incompatible with stated PUE target

Adiabatic cooling assumption in a location where water allocation could not be secured for full deployment. PUE penalty would have been 0.15.

Recovered value
€1.8M

energy cost avoided over 10-year lifecycle

Case #
Caught pre-construction
  • 25MW
  • Northern Europe
  • 2023

Tender response missed redundancy specification

Contractor bid technically lowest on price but had qualified out N+1 redundancy on the chilled water system. Procurement team had not flagged.

Recovered value
€4.2M

latent operating risk eliminated

Case #
Caught pre-construction
  • 80MW
  • Northern Europe
  • 2022

Constructability failure in modular pump room

Detail design assumed deliveries via a route that did not have crane clearance. Would have required wall demolition and rebuild mid-construction.

Recovered value
4 wk

schedule recovered

Case #
Caught pre-construction
  • 30MW
  • Northern Europe
  • 2021

BIM federated model passed clash but failed sequence

All clashes resolved in BIM at sign-off; field install impossible without removing structural beams in a sequence not supported by the steel programme.

Recovered value
€900k

demolition rework avoided

Case #
Caught pre-construction
  • 50MW
  • Northern Europe
  • 2023

Tier compliance assumption broken by ambient envelope

Reference Tier IV design assumed ambient ≤ 35°C. Site experienced 38°C peak conditions; redundancy claims would have failed audit.

Recovered value
€600k

late-stage redesign avoided

Your project, our pattern library

Every one of these started with a fresh pair of senior eyes.

That is what a Rapid Audit is. Five days, $5,000, a Top-10 Risk Register specific to your project.